← All case studies
Inotectis Advisory & Management
Case study 116 / 195
Inotectis GmbH · Advisory & Management
Case study 116

Aligning sales demand and production capacity with an advanced planning system

Performance ImprovementProcess Industries, Chemicals & Materials

Situation

A cosmetics group wanted to develop its production planning further. When sales demand changed, planners needed to be able to assess which orders could be fulfilled with the available material and existing capacity.

Challenge

The planning software had to take several dependencies into account at once. A production date that was feasible on paper was operationally worthless if material was missing. Equally important was data exchange with the ERP, including during a later release upgrade.

Approach

As head of SCM, we drove the implementation and further development of simultaneous production planning with add*ONE. We specified the requirements in the requirements specification, assessed the business case and, in the steering committee, checked the plausibility of planning results against alternative future scenarios. During the ERP release upgrade, we coordinated the changed interface architecture so that operational planning could continue.

Outcome

The company was able to respond more quickly to changes. Planning and procurement improved, and working capital could be deployed more efficiently. The operational benefit lay in being able to assess the consequences of a plan change across several dependencies before implementing it.

Inotectis GmbH · Oberer-Albaner-Weg 17 · 86911 Dießen am Ammersee · Germany
info@inotectis.com · +49 (0)8807 2258677 · inotectis.com