Operation and recovery of a server platform secured for a system change
Situation
For the operation of a business-critical internet application, a change of server hardware and application platform was due. The existing Unix environment had to be operated reliably and prepared for possible disruptions.
Challenge
Installation, maintenance and troubleshooting ran in parallel with preparation for the platform change. Recoverability after a system failure in particular could not be left until an incident occurred. Operating system environment, technical provisioning and recovery procedures had to fit together.
Approach
We took on technical tasks in operating the server environment. These included installation, fault analysis, maintenance and repair, as well as supporting the infrastructure for provisioning operating systems. When investigating incidents, we contributed to improvements and tested recovery and restart procedures in connection with the platform work.
Outcome
The operational and testing work supported preparation for the system change. Recovery procedures for the modernised environment were tested in practice and technical operating questions were resolved. The reference documents operational specialist expertise; it did not involve overall project management or a measured reduction in downtime.