Situation

For the next generation of the ERP system, production planning, procurement and distribution logistics had to define their requirements jointly. The rules on batch usage and the handovers between the operational functions and the distribution centre were particularly relevant.

Challenge

A batch can appear as stock in the system and still be blocked or unsuitable for a specific requirement. Such restrictions had to be interpreted in the same way in planning and in the downstream material flow. At the same time, existing media breaks had to be resolved before they were carried over into the new system generation.

Approach

We fed the requirements of German SCM into the business concept for Dynamics AX. With the team leads, we specified the rules for production planning, materials and logistics and clarified the functional handovers to the distribution centre. We prepared the resolution of the interface issues with the team leads and tracked the individual items in the team report.

Outcome

Defined functional roles, an SCM concept and a transparent status of the interfaces were in place for the ERP migration. Of 44 items, 15 were closed, 17 in progress and twelve open. Project management could thus plan the remaining tasks specifically into the further rollout.