Three customer websites on eleven servers transferred into hosting operations

Performance ImprovementIndustrials & Technology

Situation

An industrial company handed over several websites to a hosting provider. The technical environment comprised eleven Windows servers. The infrastructure and operations teams involved were distributed internationally.

Challenge

Technical go-live and completion of the operational takeover were two separate milestones. After go-live, it had to be clear to everyone involved which handover tasks were still open and when the websites were fully the responsibility of the operations organisation.

Approach

As the responsible boarding management, we coordinated the technical teams and brought the individual activities together in a shared handover plan. We aligned the milestones for go-live, supported the handover of the server environment and tracked the remaining boarding tasks through to completion.

Outcome

The three websites went live on eleven Windows servers. The operational takeover was subsequently completed as well. The client thus had a hosting environment taken over into regular operations.