Contract manufacturing and special finishing transferred into ERP master planning
Situation
For externally manufactured and finished items, planning relied largely on Excel lists and individual scheduling arrangements. The SCM organisation wanted to reflect these requirements in Axapta master production planning.
Challenge
The previous spreadsheet planning contained product-specific ordering and scheduling logic. With a direct transfer, it would have been difficult to tell whether a deviating proposal came from new ERP parameters or from different planning assumptions. The results therefore had to be made comparable at the level of selected items.
Approach
With the PPS team, we coordinated the introduction of master planning for contract manufacturers. Our team maintained the parameters item by item and, for selected products, compared the results from Excel and Axapta in parallel planning. We combined the tests with a review of the respective procurement and finishing strategy and planned the transfer into the live environment.
Outcome
The work package for contract manufacturer master planning was completed. The comparison planning made it transparent how the ERP planned the items tested. Product-specific, tested planning foundations were thus available for external manufacturing and finishing.