New production and logistics centre managed from site selection to start-up
Situation
A growing cosmetics group needed additional production and warehouse capacity. The new build also required decisions on filling areas, automated warehouse technology and the connection to the logistics service provider.
Challenge
A smaller filling area would have saved construction costs but would also have changed material flows. The investment decision therefore had to take into account how raw materials, packaging and finished goods would later move through the site. The relocation of existing machines also had to be aligned with the production start-up.
Approach
We took on overall project management. We translated growth expectations into space and capacity options and used the material flow to examine the consequences of a smaller filling area. For the tender, we defined the scope of work of the planners and construction partners. We then coordinated warehouse technology, automated guided vehicles and the connection to the logistics service provider. We incorporated the machine relocation and communication with the affected teams into the start-up planning.
Outcome
A shuttle warehouse and a warehouse management system were implemented at the new site. The production and logistics areas were aligned with the planned material flows. Site decision, technical design and preparation of the operational start-up thus lay within a single, end-to-end project responsibility.