Production capacity and format changeovers aligned in rolling base-load planning

Performance ImprovementProcess Industries, Chemicals & Materials

Situation

Natural cosmetics production had to allocate a changing product mix to limited line capacity. Production planning was to identify bottlenecks earlier and give manufacturing a reliable framework for order sequencing.

Challenge

A twelve-month horizon made sense for the capacity decision. The specific order sequence, by contrast, could only be fixed closer to production. Frequent format changeovers caused additional set-up and cleaning effort. Planning therefore had to bundle suitable product groups over the longer term while leaving the plant enough flexibility within the week.

Approach

With manufacturing, we agreed a twelve-month base-load plan and the division of tasks between monthly, weekly and detailed scheduling. Using ABC and format-wheel logic, we assigned products to recurring production sequences. We consolidated capacities in a planning tool and trained the planning team in using the format wheel. Detailed sequencing within the week remained with manufacturing.

Outcome

Base load, capacity requirements and format sequences could be planned together. The format wheel and the capacity tool were used operationally. The plant thus had an agreed basis for its weekly scheduling.