Production planning designed with material releases and a binding coordination horizon
Situation
At an industrial contract manufacturer, short-term changes to the production plan led to frequent interventions in sequencing. Material availability, available shifts and changeover effort were not consistently checked before scheduling.
Challenge
A production plan frozen in the short term is only robust if both material and staff are available for the orders concerned. At the same time, operations needed enough flexibility outside the fixed horizon to respond to changing customer demand. A uniform freeze period for all orders would have ignored these differing requirements.
Approach
We analysed the product range by economic importance and demand variability and, with planning and production, developed rules for fixed and conditionally changeable planning horizons. We specified material releases, changeover-oriented order sequencing and capacity alignment. For rough-cut planning and the joint alignment of the two-week plan, we developed workflows and meeting agendas.
Outcome
Operations received a fully worked-out planning procedure with defined release and coordination points. At the same time, the prerequisite for binding short-term planning was clarified: the staffing and shift model had to be decided before the fixed planning zone was introduced.