Situation

In the development of new products, raw material selection and formulation were fixed before procurement sourced the materials. Key cost drivers were therefore already determined when price negotiations began.

Challenge

A lower purchase price could only partly offset what the composition and number of raw materials meant for the cost of one kilogram of bulk. For an economic assessment, development, procurement and controlling therefore needed shared costing metrics before procurement.

Approach

Within the SCM team, we worked on the topic with procurement and controlling as a separate field of action in earnings management. We included the number of raw materials and the cost per kilogram of bulk in the review of new formulations and specified reduction targets for product costing. Monthly reporting to management was planned for further steering.

Outcome

Defined cost targets and an approach for early economic assessment were in place for new developments. The company could thus also examine formulation decisions from a procurement perspective. An actual realised cost reduction had not yet been reported.