Service management transition taken over before production start and supported into operations
Situation
At an industrial company, project responsibility for the service management transition changed shortly before production start. Interfaces to the client and helpdesk, reporting access and parts of the operating documentation were still open.
Challenge
The takeover had to happen quickly enough to support the production start. At the same time, live operation as a whole must not give the impression that all documentation for incidents was already in place. The instructions for backup, restore and reset were particularly relevant.
Approach
We took over the ongoing transition and organised the open tasks by responsibility. We aligned the communication matrix with those involved, clarified the requirements for SLA and reporting data and tracked the provision of reporting access. For backup, restore and reset, we coordinated the outstanding documentation contributions with the responsible operations functions.
Outcome
The environment reached full live operation. The remaining documentation and reporting tasks were followed up beyond go-live. It remained clear to the operations organisation which documents and access rights still had to be completed.