Sterile finishing integrated into ERP-supported master production planning
Situation
The German SCM organisation took over the planning of sterile finishing. Pharmaceutical production was to be managed through a shared master production schedule in Axapta. For this, the routings had to reflect the actual manufacturing and finishing steps.
Challenge
The takeover involved more than reassigning a planning task. An order could only be scheduled meaningfully in the ERP if the sequence of operations and planning responsibility fitted together. At the same time, there were preparations whose manufacture could not be represented using the same system logic.
Approach
Within SCM, we took over responsibility for sterile finishing planning and agreed the necessary routings with manufacturing. Our planning team adjusted the routings and transferred pharmaceutical master planning into Axapta. Using the first sterile production plans, we clarified where further adjustments to the manufacturing processes were needed.
Outcome
The pharmaceutical master production schedule was in use. The first sterile production orders were planned in Axapta. The organisation thus had an operational basis for finishing planning and could handle product-specific exceptions separately.