Comprehensive supply chain realignment for a cosmetics company
Client
Cosmetics company with 2,000 employees and €500 million annual revenue. Produces exclusively own brands, operates worldwide, around 20,000 SKUs.
Project scope
The project aimed to optimise the entire supply chain of a globally active natural cosmetics company and adapt it to future growth. Challenges such as lack of reliability, high process costs and inefficient planning methods were addressed by introducing scalable processes. The focus was on introducing a uniform S&OP process, improved production and procurement planning, and the integration of modern IT systems.
Project framework
Duration 15 months. Interdisciplinary project team from supply chain, production, procurement and sales. Core processes: strategy, organisation, skills · order management and forecasting processes · lean production and S&OP · tools and data management · sourcing and packaging · distribution network · production planning (MPS/MRP) · costs and controlling · KPI system · advanced planning functions including IT integration.
Objectives
- Improving delivery reliability and stabilising the supply chain
- Introducing an integrated S&OP process to harmonise planning and forecasting
- Reducing manual effort through standardisation and IT integration
- Optimising inventories and improving material flows
- Creating scalable processes for future growth
Implementation
- Project organisation: steering team with regular meetings
- Workshops: cross-functional and department-specific, on planning, forecasting and inventory management
- IT integration: introduction of a modern tool for sales and production planning
- Process adjustments: standardised planning and ordering processes with clearly defined roles
- Quick wins: improved production and procurement planning, optimised safety stocks
Role of Inotectis
- Leading the project with responsibility for budget, schedule and achievement of objectives
- Facilitating cross-functional workshops and coordinating the sub-projects
- Setting up a dedicated SCM organisation with clear responsibilities
- Developing and introducing an S&OP process and KPI dashboards
- Monitoring the implementation of new processes and IT systems
Results
- Introduction of a dedicated SCM department, efficiency increased by 20%
- Delivery reliability above 97% for cosmetic products and 95% for other product categories
- Inventories reduced by 25% through better planning and safety stock optimisation
- Improved machine running time and production utilisation through optimised batch planning
- KPI cockpit for transparency and better management along the supply chain