Transition of a large-volume integrated facility services contract
Situation
A newly won nationwide integrated facility services contract with revenue of around €500 million and some 6,000 employees had to be transferred from the previous operating model into a new service organisation within a tight time frame.
Challenge
Numerous sites, employees, technical and infrastructure services and existing processes had to be taken over without disrupting ongoing operations.
Approach
Responsibility as Transition Director for the target organisation, due diligence, set-up of units and branches, recruitment, transfer of specialists and managers, and cutover planning; additionally, operational responsibility for the southern region.
Outcome
The new service organisation was set up on schedule and the defined content and timing objectives of the transition were achieved. The case demonstrates in particular experience in the large-scale takeover and stabilisation of technical and infrastructure services.